Project Management

Q. 1884 :- 5. How to assign task to work order? Also how to assign material /labour /machinery in any task?

Solutions :-

BOQ which you have imported > click on Project manager > BOQ list will show > select the tasks you will a lot to subcontractor >click on edit > select contract > select work order > click on save >

 

Click on edit.

 

 

Select Contract > select work order > click on save this task will get assigned to the subcontractor.

 For planning material / labor / Machinery in any task > select the Item / Labor / Machinery / fill the quantity and rate.

Click on save.

 